San Jose Data Center Network Maintenance - March 16th 20:45 EDT
Scheduled Maintenance Report for Fuze
Completed
The scheduled maintenance has been completed.
Posted Mar 17, 2019 - 00:46 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 16, 2019 - 20:45 EDT
Scheduled
What are we doing?
Fuze will be conducting required maintenance in the San Jose Data Center to optimize configuration on network equipment.

Who is affected?
Customers whose primary services are hosted on the San Jose Data Center who are also using either Fuze Meetings or Voice services.

When are we doing this?
Start: Saturday, March 16th 20:45 EDT (00:45 GMT)
End: Saturday, March 16th 24:00 EDT (03:45 GMT)

What will you experience during the window?
You may experience a momentary interruption of service (up to 30 seconds) throughout this 3 hour window while the new configuration is being applied.

What do you need to do?
If you experience any issues with Fuze Meetings or Voice services during this time we recommend waiting up to 60 seconds and trying again.

What happens if it doesn't go as planned?
Maintenance will be reverted.

Who should you contact with questions?
Please reach out to us; we would be happy to talk to you!

U.S. Toll Free +1 866 379 9442
United States +1 617.603.2299
Australia +61 2 8607 8029
France +33 97 518 6686
Germany +49 32 22 109 6038
Greece +30 211 198 3039
Ireland +353 76 888 7202
Israel +972 3 763 0658
Italy +39 02 94 75 2581
Japan +81 34 589 4674
Netherlands +31 20 241 0144
United Kingdom +44 330 808 0131

or visit our support page at fuzecommunity.force.com/support.
Posted Mar 12, 2019 - 15:46 EDT
This scheduled maintenance affected: Voice Services - North America (San Francisco, CA), Legacy FCC Services - North America (San Francisco, CA), and Fuze Meetings - Global (San Jose, CA).